Beaver Creek Project Construction 

Construction for the the Beaver Creek Clean River Project includes five phases beginning in Spring of 2021 until Project completion in December 2022. Please check this page for updates to the construction schedule, or sign up to receive updates. Construction activities will include soil testing and continuous air quality monitoring - shown in real time via PurpleAir Widget on this page (view the Air Quality Index.)

View an interactive map that shows the Project's tunneling progress, photos, and aerial images. 

Map of construction phases and timelines for the Beaver Creek Clean River Project Opens in new window


Two Week Construction Look Ahead

  1. Rebecca Caldon, P.E.

    Engineering
    Phone: 518-434-5104

Loading PurpleAir Widget...

Treatment Facility (Phase 5) and Diversion Pipe (Phase 3)

Timeframe

Work 

Impacts

May 10, 2021 - Fall 2022Excavation and tunneling.Closure of road from TOAST Elementary to MLK Jr. Blvd. Temporary Traffic Pattern (shown at the bottom of this page) 


Lincoln Park Bowl Athletic Field (Phase 5)

Timeframe

Work 

Impacts

May 2021 - June 2022 Fill added. Regrading of fields and new grassClosure of eastern half of Bowl and Lincoln Park Road (south)
September 2021 - May 2023Fill added. Regrading of fields and new grassClosure of western half of Bowl and Lincoln Park Road (south)


New Sewer Pipe (Phase 4)

Timeframe

Work/Location

Impacts

July 2021 - Fall 2021Excavation (Lincoln Park near Morton and S. HawkReduced access, parking restrictions on Morton Ave next to Lincoln Park. Local 2-way traffic only on S Hawk St.
July 2021 - Fall 2021Excavation (S Hawk and Third Ave) Parking Restrictions on S. Hawk and Third Ave. Closure of bend at St Hawk St. and Third Ave. Local 2-way traffic only on Third Ave.  View Map
August 2021 - Winter 2021
Tunneling (Lincoln Park near Morton and Hawk)
 View the tunneling progress map.
Reduced access, parking restrictions on Morton Ave next to Lincoln Park


Lincoln Park Ravine (Phase 3)


Timeframe

Work 

Impacts

Summer 2021 - Fall 2023Grading ImprovementsReduced access
Fall 2022Reinstall Community GardenReestablished and improved
2022Design of Ravine GardenFuture Improvement


Third Ave and Pearl St. (Phase 1)


Timeframe

Work 

Impacts

June 1 - July 9Installation of Diversion StructureLane and parking closures

Temporary Traffic Pattern at TOAST Elementary for Duration of Construction.

Temporary Traffic Pattern